Andy Sloan
COWI
Managing Director
The Glendoe Hydro Electric project was the last major hydro scheme constructed in the UK and for the preceding three decades. Shortly after opening there was a catastrophic collapse in the headrace tunnel and extensive remedial works were required to recover the scheme. Andy was closely involved with events after the collapse.
In this presentation he will discuss the collapse, the mechanisms involved, some lessons learned and describe the recovery project. This talk is set against the back-drop of a potential renaissance of pumped storage hydro in Scotland.
COWI
Managing Director

This webinar will give an overview of the use of GIS in a military context and how its principles and approaches can enhance design, collaboration, decision-making and delivery in construction projects.


This is a fantastic opportunity for you gain insight into a major client approach to risk and the value of undertaking site investigation.