Year
2014-17Duration
3 yearsCost
£56mLocation
United KingdomProject achievements
Economy boosted
Lots of local businesses involved with project.
Solved the problem
Increased road space to meet increase in vehicles.
Used engineering skill
Wide range of works took place around traffic.
Add more lanes to a 6km trunk road without stopping the traffic
The 6.4km Coal House to Metro Centre stretch of the A1 used to be the third most congested link on the national trunk road network and the most congested regionally.
It carried more than 116,000 vehicles a day – double its original predicted capacity.
This meant stationary or slow moving traffic in and out of Gateshead and Newcastle resulting in long delays and slower journey times.
To solve this meant adding one lane in each direction within the limits of the existing highway boundaries.
Did you know …
-
For vehicle breakdowns the project used a motorcycle to access a stranded car quickly and then tow it away.
-
300 people were involved with the construction phase.
-
78% of project spend was local with 59% spent with local businesses
Project achievements and benefits
The scheme had to deal with challenging ground conditions along with significant traffic management restrictions to maintain two lanes running in each direction during the daytime period.
It also involved significant modifications to the existing drainage and sewer networks along with the installation of new road lighting, gantries, variable message signs and CCTV infrastructure.
Keeping the public and workforce moving and safe was crucial. The site was extremely busy and congested – over 90 million vehicles across the life of the project.
750,000 man hours were worked and incident free. The project did not incur a single road traffic accident. It earned top marks from industry health and safety monitors.
A new footbridge was built for non‐motorists and maintained the important link between the two communities split by 10 lanes of traffic.
Regular meetings were held with key stakeholders such as Gateshead MBC and Metro Centre to understand their concerns and requirements. Work was planned with the Metro Centre for peak retail periods to ensure disruption was minimised.
Over 80 people came along to an ‘open doors’ weekend. Visitors received an escorted drive‐through site tour and were encouraged to ask questions.
Environmental benefits
- Congestion and vehicle emissions reduced. Increased journey times give added social and economic benefits.
- Dealing with excavated material: a local processor agreed to treat, crush and re‐use this material without a cost to the project. 97% of waste was diverted from landfill.
- A number of activities were monitored for noise, dust, light and vibration to ensure all levels were kept within acceptable limits.
- Japanese Knotweed was found extensively across the site. To mitigate the risk of this pest spreading and to reduce the amount taken to landfill it was either left in place and fenced off or excavated out and transported to an onsite reception pit. Both areas will be treated within the 5 year landscape maintenance period.
- In 2016 the project was awarded a Silver Green Apple for the Built Environment Award.
- Considerate Constructor Scheme Assessment scored of 47 and 48 out of a possible 50 and the scheme was nominated for a 2017 gold award.
People who made it happen
- Client: Highways England
- Contractors: Parsons Brinkerhoff, Arup, Balfour Beatty